# Field Print Packs: Standard Page Sets for Every Job

> Print page sets for every job type: installation, commissioning, service visit, CT and meter, battery and BMS, photo evidence, handover, and field audit.

Every page on this site prints clean from your browser — press Ctrl/Cmd-P and the page formats for paper. These eight packs are the standard sets a crew carries for each job type. Pull the pages for your job, print them at the office or a print shop, and carry them to site. Kent-stamped combined PDF packs are published on this page as they are released.

<Tip>
  Print per page for the cleanest pagination. The checklists and the [Handover Form](/handover/handover-form) are designed to be filled by hand in the field. The [mixed-fleet cheat card](/mixed-fleet/cheat-card) prints as a single sheet — every crew working both platforms carries one.
</Tip>

## The eight standard packs

<CardGroup cols={2}>
  <Card title="1 · Installation Pack">
    The pages a crew needs from van to wall.

    **All platforms:** [Safety First](/safety/safety-first) · [PPE & Tools](/safety/ppe-and-tools) · [Choosing the Location](/environment/choosing-the-location) · [Mounting & Service Access](/environment/mounting-and-service-access)

    **Kent M1 add:** [Mounting](/m1/mounting) · [PV Wiring](/m1/pv-wiring) · [AC Wiring](/m1/ac-wiring) · [Battery Wiring](/m1/battery-wiring)

    **Kent G3 add:** [Mounting](/g3/mounting) · [PV Wiring](/g3/pv-wiring) · [AC Wiring](/g3/ac-wiring) · [Battery Wiring](/g3/battery-wiring)
  </Card>

  <Card title="2 · Commissioning Pack">
    Everything needed to witness, test, and sign off a new installation.

    [Common Commissioning Checklist](/checklists/common-commissioning) · [Kent M1 Commissioning Checklist](/checklists/m1-commissioning) or [Kent G3 Commissioning Checklist](/checklists/g3-commissioning) · [Energy-Flow Test](/ct-meter/energy-flow-test) · [Site Photo Checklist](/environment/site-photo-checklist)
  </Card>

  <Card title="3 · Service-Visit Pack">
    The minimum a service technician carries for a reactive or scheduled visit.

    [Isolation & Shutdown](/safety/isolation-and-shutdown) · [When to Escalate](/troubleshooting/when-to-escalate) · plus the symptom page matching the service ticket (start from [Troubleshooting: Not Starting](/troubleshooting/not-starting) and follow the fault)
  </Card>

  <Card title="4 · CT & Meter Pack">
    For CT placement, direction confirmation, and zero-export setup or diagnosis.

    [CT Basics](/ct-meter/ct-basics) · [Direction & Location](/ct-meter/direction-and-location) · [Meter & Phase Matching](/ct-meter/meter-phase-matching) · [Wrong-CT Symptoms](/ct-meter/wrong-ct-symptoms) · [Kent M1 CT & Meter](/m1/ct-and-meter) or [Kent G3 CT & Meter](/g3/ct-and-meter)
  </Card>

  <Card title="5 · Battery & BMS Pack">
    For battery installation, BMS commissioning, and communication checks.

    [Battery Safety](/battery/safety) · [BMS Comms Basics](/battery/bms-comms-basics) · [Cable Checks](/battery/cable-checks) · [Kent M1 Battery Wiring](/m1/battery-wiring) or [Kent G3 Battery Wiring](/g3/battery-wiring)
  </Card>

  <Card title="6 · Photo-Evidence Pack">
    For commissioning sign-off and audit-ready photo records.

    [Site Photo Checklist](/environment/site-photo-checklist) — every 📷 point across the commissioning and test pages belongs in this record. Print and tick as you shoot.
  </Card>

  <Card title="7 · Handover Pack">
    Everything the customer receives and signs at the end of the job.

    [Explaining the System](/handover/explaining-the-system) · [Backup Can & Can't](/handover/backup-can-and-cant) · [Battery Expectations](/handover/battery-expectations) · [Warranty-Safe Usage](/handover/warranty-safe-usage) (the DO/DON'T card) · [Handover Form](/handover/handover-form)
  </Card>

  <Card title="8 · Field-Audit Pack">
    For auditing an existing installation against commissioning claims.

    [Common Commissioning Checklist](/checklists/common-commissioning) · [Site Photo Checklist](/environment/site-photo-checklist) · [Wrong-CT Symptoms](/ct-meter/wrong-ct-symptoms) · [Handover Form](/handover/handover-form)

    The audit walks what commissioning claimed. Bring the original handover form from the job record where available.
  </Card>
</CardGroup>

## Mixed-fleet crews

If your crew works on both Kent M1 and Kent G3 sites, add the [Mixed-Fleet Cheat Card](/mixed-fleet/cheat-card) to every pack. It prints as a single A4 sheet with the key differences — torque, TOU units, DIP positions, altitude, GEN port rules, and the crossover-cable rule that is the same on both platforms.

<Note>
  The cheat card is the fastest way to prevent platform-mix mistakes. Print one per technician, laminate it, and keep it in the toolbag.
</Note>

## When to escalate

<Note>
  **Escalate to Kent New Energy service only** — through your registered Kent partner channel or the Kent service desk details on your work order. Do not contact any third-party or component-manufacturer support line for a Kent-branded system: tickets outside the Kent channel are not tracked, not covered, and can void warranty handling.
</Note>