Common
Every Kent hybrid site, both platforms — run this first.
Kent M1
Single-phase platform additions.
Kent G3
Three-phase platform additions.
Pass/fail discipline
- Every item states its pass condition. Meet it, tick it. Cannot meet it — the item is a fail, and a failed safety or sequence item stops the commissioning until fixed.
- 📷 marks items that require a photo in the record — the shot list is the Site Photo Checklist.
- Items carrying a KNB-VAL tag have a value pending Kent confirmation: apply the stated interim rule exactly and record what you measured.
The commissioning record
- The completed checklist(s) with every tick.
- The full photo set, uploaded same-day.
- Settings snapshot — photograph every settings screen after final configuration; this is the restore point for future service.
- Customer sign-off — walkthrough given, DO/DON’T handover card left on site, signature captured with the record.
Common mistakes
- Ticking now, photographing “later” — later has a 40% survival rate.
- Treating a KNB-VAL interim rule as optional because “the real number is coming”.