Before you start
- Unit firmly mounted, accessible for service, ventilation space clear, nothing on top.
- Inverter and accessories correctly connected; cables routed safely and protected.
- Warning labels affixed and durable.
- Antenna fitted to its port.
- Clip-on DC ammeter in the kit — the 0.5 A DC-switch rule applies to every DC-switch operation.
Power ON — the G3 sequence
Kent G3 power ON = AC first; power OFF = battery first (exact reverse) — figure KNB-SVG-03
- Measure PV string and battery DC voltage; confirm polarity.
- Measure grid AC voltage and frequency — within the local standard.
- Close the external grid AC breaker — the control board powers up.
- Complete the first-time Quick Setting (below).
- Close the inverter PV DC switch and the battery breaker — the system starts.
Quick Setting — in this order
On first commissioning the HMI walks the Quick Setting sequence:Kent G3 HMI navigation mock-up (indicators, 4 keys, Quick Setting) — figure KNB-SVG-10
- Inverter time — date and time.
- CT / Meter setting — select CT or meter; set the installation location (Grid side / Load side / Grid + PV inverter — grid connection point is the standard); CT direction (correctly installed = Forward; select Reversal only to correct a physically reversed CT); CT ratio exactly per the shipped CT nameplate. [KNB-VAL-08]
- Grid code — only per the Kent parameter sheet for the site’s DISCOM; the three-level OV/UV/OF/UF protection sets load from the grid code — no manual entry. [KNB-VAL-01]
- Storage mode — Self-use / Selling first / Off-grid (exclusive); see Settings Reference.
- Battery setting — select the battery brand entry: for the Kent Lithium Battery the LV Pylon-family entry (PYLON_LV); set max charge/discharge current to the bank’s capability; confirm live SOC on the screen before closing the job. 📷
Selecting no battery model (or the wrong one) raises a battery-name failure alarm; “No
Battery” / “No Meter” exist to suppress alarms only while that hardware is genuinely absent.
Defaults to know: overdischarge SOC 20 %, force-charge SOC 10 %, battery reserve 80 %
(range 5–95 %). The ordering rule is Force-charge SOC < Overdischarge SOC < Recovery SOC.
Function tests before sign-off
- Battery both ways: force charge and discharge; currents within platform and pack limits.
- CT sanity: grid on, PV off → import on all three phases; per-phase load steps → each phase responds on its own CT. 📷
- Per-phase heavy-load test and unbalanced-output state check. [KNB-VAL-06]
- Backup transition: open the grid breaker with real essential loads — loads ride through; clean return.
- Zero-export witness on export-limited sites — settings and the “Max export power = 0” rule on Settings Reference.
- Parallel sites: master address = 1, slaves sequential; DIP ends ON; every unit’s datalogger fitted.
Common mistakes
- DC switch operated without the 0.5 A clamp check.
- CT ratio assumed at 3000 when the box kit shipped the 2000-ratio CT. [KNB-VAL-08]
- “Reversal” selected to hide a physically backwards CT instead of re-clamping it — fix the hardware, use Forward.
- Carrying Kent M1 habits (menu password, DIP positions, TOU units) onto this platform.