Skip to main content
Ten questions from the Kent M1 group. Work through all ten before scrolling to the key. Suggested pass mark: 8 / 10. Each miss points to a source page — re-read it, not the whole group.

Questions

1. The Kent M1 Hybrid Inverter is a:
  • A. Three-phase platform with split-phase output
  • B. Single-phase platform — one AC grid input and one AC backup output
  • C. Three-phase platform sharing a single grid connection
  • D. Single-phase platform with three-phase battery input

2. The maximum PV string open-circuit voltage (Voc) the Kent M1 accepts is:
  • A. ≤ 450 V
  • B. ≤ 500 V
  • C. ≤ 550 V
  • D. ≤ 600 V

3. Kent M1 AC terminal torque is:
  • A. 0.5 N·m
  • B. 1.2 N·m
  • C. 2.5 N·m
  • D. 4–5 N·m

4. Dual PE (protective earth) termination on the Kent M1 AC port is:
  • A. Optional — single PE is adequate for residential installations
  • B. Required only on TT earthing systems
  • C. Mandatory on all Kent M1 installations
  • D. Required only when the battery is connected

5. Kent M1 backup maximum output current by model — 3 kW / 5 kW / 6 kW — is:
  • A. 10 A / 20 A / 25 A
  • B. 16 A / 32 A / 40 A
  • C. 15 A / 25 A / 30 A
  • D. 20 A / 30 A / 35 A

6. The Kent M1 grid-charge function ships from the factory:
  • A. Enabled by default for lithium batteries
  • B. Disabled by default — enable it deliberately where the design requires it
  • C. Controlled automatically by the BMS based on SOC
  • D. Enabled only when the battery falls below 20 % SOC

7. Kent M1 Time-of-Use (TOU) programming uses:
  • A. 6 time slots tiling 24 hours, with discharge power set in watts
  • B. 6 + 6 windows, with charge/discharge current set in amps
  • C. A single day/night pair with a percentage of rated power
  • D. 4 slots with start time, end time, and a mode flag only

8. For Kent M1 parallel systems, the DIP switch scheme at the first and last unit is:
  • A. A 2-way switch with both pins ON at first and last unit
  • B. No DIP switches — addressing is software-only
  • C. A 3-way switch with pins 1 & 3 enabled at first and last unit
  • D. A 3-way switch with all three pins ON at every unit

9. The first step of the Kent M1 power-ON sequence is:
  • A. Turn on the battery button switch
  • B. Close the PV DC disconnect switch
  • C. Close the AC protection switch on the grid side
  • D. Press the inverter power key on the display

10. The Kent M1 GEN port accepts:
  • A. A three-phase generator of any rated size
  • B. Grid-tied micro-inverters only
  • C. A single-phase generator up to 6 600 VA / 30 A
  • D. Nothing — the GEN label is a monitoring input only

Answer key

QAnswerWhy
1BThe Kent M1 is a single-phase hybrid inverter. One AC grid connection, one AC backup output. Not to be confused with the three-phase Kent G3.
2BThe Kent M1 maximum PV open-circuit voltage is 500 V. String design must keep Voc at worst-case (cold) temperature below this limit.
3BKent M1 AC terminal torque is 1.2 N·m. The Kent G3 is 4–5 N·m — a common mix-up on mixed-fleet crews.
4CDual PE is mandatory on all Kent M1 installations. A single PE connection is not compliant.
5C15 A (3 kW) / 25 A (5 kW) / 30 A (6 kW). Size the essential panel to the specific model’s figure — 30 A is only valid for the 6 kW unit.
6BGrid-charge ships disabled by default on the Kent M1. Enabling it is a deliberate design choice — not automatic. On outage-first homes, enable it at commissioning.
7AThe Kent M1 TOU uses 6 time slots tiling 24 hours, with power set in watts. The Kent G3 uses amps — a common platform-mix error.
8C3-way DIP switch, pins 1 and 3 enabled at the first and last unit in the parallel chain.
9CThe Kent M1 power-on sequence: close AC protection switch first. Power-off is the reverse — battery off first.
10CThe Kent M1 GEN port accepts a single-phase generator up to 6 600 VA / 30 A. The Kent G3 GEN port is three-phase only.