Platform pre-checks
Verify these items before the G3 power-up sequence.- Altitude — confirm the site is at or below 4000 m. Pass: confirmed.
- Mounting angle — unit mounted vertical within ±5°; clearances per the G3 figures including ≥ 500 mm from the ground at the bottom and fan-side clearances (air in from the left, out to the right) unobstructed. Pass: angle measured; clearances measured and photographed. 📷
- Grounding — external grounding conductor and heat-sink ground terminal connected per the manual figure. Pass: both conductors landed and photographed. 📷
- Phase rotation — check with a rotation meter at the grid terminals; match the utility’s L1–L2–L3 to the inverter’s AC terminals. Pass: rotation correct; no phase alarm at boot.
Power-up and first configuration
Use the on-device HMI (four-key navigation). Access the installer session before entering settings.DC switch discipline
Operate the DC switch only when string current is below 0.5 A — verify with a clamp ammeter before every operation. This is an arc-prevention rule, not a guideline. Pass: rule followed at every DC switch operation.
Power ON in the G3 sequence
Grid AC ON first → complete first-time setup → then PV DC switch ON → battery breaker ON. Power-off is the reverse: battery first. Pass: clean boot with no fault codes.
Use only the partner-gated password for advanced settings
Day-to-day commissioning uses the standard HMI menus. The professional menu requires the partner-gated installer password — never shared, never bypassed. Pass: no unauthorized professional-menu changes made.
Complete Quick Setting in the HMI order
Time → Meter/CT → Grid code → Storage mode → Battery setting. Do not skip steps or change the order. Pass: each step confirmed and photographed. 📷
Select the correct battery model
Select the LV battery-brand protocol family — PYLON_LV — for the Kent F1 battery. Selecting nothing, the HV entry, or the wrong model raises a BatName-FAIL alarm. Pass: battery model set; live SOC displayed. 📷
Three-phase behaviour
- Per-phase load test — step a known load on each phase individually; each phase must feed its own load with correct CT mapping. Pass: per-phase power readings correct on the HMI.
- Backup transition — open the grid breaker with real essential loads connected on the Backup port. Pass: loads ride through the transfer; clean reconnect on grid restore.
Alarm handling rule
- One-restart discipline at boot — if any alarm shows at first boot, power off in the correct sequence, wait 5 minutes, and restart once. If the alarm persists, stop and escalate — do not cycle repeatedly. Pass: rule followed; alarm code and result recorded and photographed. 📷
Common mistakes
- Operating the DC switch under load “because it clicked fine last time” — the 0.5 A rule is an arc-prevention rule that protects both the switch and the installer.
- Skipping the installer login and configuring from a user session — advanced parameters are not accessible or accurate in a user session.
- Selecting PYLON HV (or leaving the battery model blank) instead of PYLON_LV.
- Carrying Kent M1 menu passwords, parallel DIP positions, or battery menu habits onto this platform.