When to use a meter instead of direct CTs
A supported energy meter carries its own CTs and reports over RS485 to the inverter. Use a meter scheme when:- The grid connection point is beyond the CT lead’s design reach [KNB-VAL-23]
- The site design shipped with a meter scheme
- AC-coupled metering is required at a multi-source site
Kent M1 CT & Meter
Supported meters, terminal mapping, 3-CT single-phase schemes, and 6-CT three-phase AC-couple schemes are on the Kent M1 CT & Meter page.
Kent G3 CT & Meter
Meter scheme, pin map, kit ratios, and installation location options (Grid side / Load side / Grid + PV inverter) are on the Kent G3 CT & Meter page.
RS485 polarity — A on A, B on B
Meter communications fail on swapped polarity more than any other wiring error. Land A on A and B on B at every termination point, using signal name rather than pin number as your reference — on the Kent G3 the meter end and the inverter end use different pin numbers for the same signal pair.| Symptom | Likely cause |
|---|---|
| Meter comm fault, no grid data on display | A/B swapped at one end, or meter supply circuit is dead |
| Comm fault only during backup test | Meter powered from a circuit that goes dead when grid is lost |
Three-phase discipline: match everything, per phase
On a Kent G3 three-phase installation, three CTs must agree with three conductors and three terminal pairs simultaneously.Match CT to conductor by phase
The L1 CT clamps on the L1 conductor. L2 on L2. L3 on L3. Right phases with crossed leads is still wrong.
Match CT leads to the correct terminals
The L1 CT’s leads land on the CT-L1 terminal pair. L2 leads on CT-L2 terminals. L3 leads on CT-L3 terminals.
Check arrow direction on every CT
Every CT’s arrow toward the grid — the universal Kent rule applies on all three phases.
AC-coupled and multi-source sites
Where an existing grid-tie PV inverter shares the site, the metering scheme must account for its generation:- Kent M1 AC-couple schemes place a CT on the grid connection and a second CT on the existing solar inverter’s output — detailed on the Kent M1 CT & Meter page.
- Kent G3 offers the Grid + PV inverter meter placement option for the same scenario.
Retrofit expectation for third-party grid-tie inverters: a third-party grid-tie inverter on the grid side has no control channel to the Kent hybrid. The system can meter its output but cannot command it to reduce generation. This has a direct impact on zero-export performance — plan export behaviour accordingly and engage Kent service before quoting a multi-source retrofit.
Common mistakes
A/B swapped at one end only — 'tested fine' with a continuity beep
A/B swapped at one end only — 'tested fine' with a continuity beep
A continuity test on swapped RS485 polarity passes because both wires are present. It fails at comm. Wire by signal name: A on A, B on B.
Meter powered from a circuit that is dead during backup operation
Meter powered from a circuit that is dead during backup operation
Grid data vanishes exactly when you need it most. Power the meter from a circuit that survives a grid outage.
Three CTs clipped in a hurry — right directions, wrong phases
Three CTs clipped in a hurry — right directions, wrong phases
Speed at the enclosure costs an hour of troubleshooting. Match conductor, leads, and terminals per phase before closing up.
Running both CTs and a meter simultaneously 'to be safe'
Running both CTs and a meter simultaneously 'to be safe'
Only one sensing scheme per site. Two schemes conflict and produce corrupted grid data.