Phase sequence
Terminal labels read W(L3) · V(L2) · U(L1) · N · PE on all three ports. Match each terminal to the utility’s actual phases and verify rotation with a rotation meter — wrong rotation blocks grid sync and raises phase alarms.Cables and torque
Kent G3 AC grid and backup terminals — figure KNB-G3-CR-06
- Strip 13 mm, crimp R-type connectors, bolt down with a torque wrench.
- Terminal maximum temperature is 85 °C — heat at a terminal means workmanship, not load.
- The backup loads panel must not be electrically connected to the main service panel.
Size for pass-through + charging, not output
The grid side carries battery charging and up to 50 A of continuous AC pass-through to backup loads. Grid-side max input current is 22.8 / 27.3 / 34.2 A per phase (10/12/15 kW) with grid-side input power up to 15 / 18 / 22.5 kW — about 1.5× the inverter’s own rating. Cable and OCPD are sized to these input figures plus local code, never to the output kW alone.Backup behaviour to know while wiring
- Transfer < 10 ms class; overload 2× rated power for 10 s; max phase imbalance 50 %.
- Per-phase promises follow the platform’s unbalanced-output rules — see Settings Reference and [KNB-VAL-06].
Common mistakes
- U and W swapped “because the colours matched” — rotation meter, always.
- Grid OCPD sized to 15 kW output on a 15 kW unit that draws 34.2 A per phase charging.
- Backup subpanel bridged to the main panel during “testing” and never removed.
- Terminals torqued by feel — 4–5 N·m is a torque-wrench number.