Skip to main content
The Kent G3 has three AC terminal sets — GRID, Backup, and GEN — with a single phase-order rule that determines whether the machine ever syncs to the grid. Get the sequence right first, then work through the cable sizes and torque.
DANGER — verify 0 V AC at all conductors with the OCPDs open before touching any terminal.

Phase Sequence

Terminal labels on all three ports read W(L3) · V(L2) · U(L1) · N · PE. Match each terminal to the utility’s actual phases, then verify rotation with a phase rotation meter before energizing. Wrong rotation blocks grid sync and raises phase alarms.

Cables and Torque

PortCross-sectionTorque
AC Grid6–10 mm² (8–6 AWG)4–5 N·m
AC Backup4–10 mm² (10–6 AWG)4–5 N·m
AC GEN4–10 mm² (10–6 AWG)4–5 N·m
PE (all ports)10 mm² (6 AWG)4–5 N·m
  • Strip 13 mm, crimp R-type connectors, and torque with a torque wrench — not by feel.
  • Terminal maximum temperature is 85 °C. Heat at a terminal means a workmanship issue, not an overloaded circuit.
  • The backup loads panel must not be electrically connected to the main service panel.
4–5 N·m is this platform’s AC terminal torque. If you also work on the Kent M1, its AC torque is significantly lower. The figures are platform-specific and must not cross over. Side-by-side values live only on the Mixed-Fleet Cheat Card.

Size for Pass-Through Plus Charging, Not Output

The grid side carries both battery charging current and up to 50 A continuous AC pass-through to backup loads simultaneously. Grid-side max input current is:
ModelMax input current per phaseMax grid-side input power
Kent G3 10KW22.8 A15 kW
Kent G3 12KW27.3 A18 kW
Kent G3 15KW34.2 A22.5 kW
Size cables and OCPDs to these input figures plus local code requirements. Never size to the output kW rating alone — the grid side draws roughly 1.5× the inverter’s own rated output.

Backup Behaviour to Know While Wiring

  • Transfer to backup: < 10 ms
  • Overload capacity: 2× rated power for 10 seconds
  • Maximum phase imbalance: 50%
Per-phase backup promises follow the platform’s unbalanced-output rules — see the unbalanced-output validation warning in Settings Reference.

Common Mistakes

  • U and W swapped because the wire colours seemed to match — use a rotation meter, always.
  • Grid OCPD sized to the output kW on a 15 kW unit that draws 34.2 A per phase while charging.
  • Backup subpanel bridged to the main panel during testing and the bridge never removed.
  • Terminals torqued by feel — 4–5 N·m requires a torque wrench.